18 December 2023 → 25 January 2024
Initial Feedback Period Feedback (Plan of Management)
01 March 2024
Extension of Initial Feedback Period
March 2024
Project expanded to include a Master Plan
06 June → 12 July 2024
Community and Stakeholder engagement to inform Master Plan and Plan of Management
July 2024
Consideration of Initial Feedback
August → December 2024
Preparation of Draft Master Plan and Plan of Management
February 2025
Report draft Plans to Council
March 2025
Refer draft Plans to Crown Land for owner's consent to exhibit
March → July 2025
Crown Land review (can take up to 6 months)
August → September 2025
Public Exhibition of Draft Plans
November 2025
Report to Council on Public Exhibition Results
December 2025
Finalisation