18 December 2023 → 25 January 2024

Initial Feedback Period Feedback (Plan of Management)

01 March 2024

Extension of Initial Feedback Period

March 2024

Project expanded to include a Master Plan

06 June → 12 July 2024

Community and Stakeholder engagement to inform Master Plan and Plan of Management

July 2024

Consideration of Initial Feedback

August → December 2024

Preparation of Draft Master Plan and Plan of Management

March 2025

Report draft Plans to Council

March 2025

Refer draft Plans to Crown Land for owner's consent to exhibit

March → September 2025

Crown Land review (can take up to 6 months)

September → October 2025

Update PoM based on Crown Land feedback

November 2025

Council consideration of updated PoM

February → March 2026

Public Exhibition of Draft Plans (TBA)

May 2026

Report to Council on Public Exhibition Results

June 2026

Finalisation