February 2025: Exhibition of the Master Plan and Plan of Management
A big thank you to our community, partners and stakeholders who have been with us throughout the planning process of Merriman Reserve. We are finalising our Master Plan and Plan of Management, which will help inform Council upgrades over the next 10 years. Since commencing the consultation in November 2021, we have received over 220 submissions and identified the following key themes:
Enhanced community access and amenities
Improved foreshore and beach access
Increased green spaces and recreational opportunities
Greater connectivity through pedestrian walkways and shared paths
If you would like to provide feedback or comments on the Plans, we encourage you to complete our online feedback form or return a hard copy submission. Consultation will be open from 5 February to 21 March 2025.
If you are returning a hard copy submission, please quote SF24/8017 - Public submission Merriman Reserve at the beginning of your submission and return in person to Georges River Council Civic Centre or Libraries, via email: mail@georgesriver.nsw.gov.au or post to PO Box 205, Hurstville BC NSW 1481
Pop-in to our Pop-up at Merriman Reserve Between 10.00am to 12.00pm, Saturday 22 February, our team will be on site at Merriman Reserve. Come along to chat with our staff and consultants about the Plans and ask us questions. No registrations required.
Attend our Pubic Hearing Under section 40A(1) of the Local Government Act 1993, Council is organising a public hearing into the proposed changes to the land categorisation of Merriman Reserve. The public hearing will be held on 4 March 2025 from 6:00 pm to 7:00 pm at Georges River Civic Centre, corner of MacMahon and Dora Streets, Hurstville. Register for the hearing
History and previous steps
March 2024 - Consent to Exhibit
On 11 March 2024, Council's Environment and Planning Committee considered a report presenting a draft Merriman Reserve Master Plan and Plan of Management for exhibition.
The recommendation of the Environment and Planning Committee was considered by Council on 25 March 2024 who resolved:
That Council notify the draft Merriman Reserve Plan of Management and Master Plan to the NSW Department of Planning, Housing and Industry, as the representative landowner of part of the land under section 39 of the Local Government Act 1993, to obtain owner's consent prior to public exhibition.
That Council seek written consent from the NSW Department of Planning, Housing and Infrastructure to adopt the draft Plan of Management, in accordance with section 3.23(6) of the Crown Land Management Act 2016.
That Council delegates authority to the General Manager to make any further amendments to the draft Merriman Reserve Plan of Management and Master Plan to address any points raised by the NSW Department of Planning, Housing and Infrastructure and make minor modifications to any numerical, typographical, interpretation and formatting errors if required.
That Council endorse the draft Merriman Reserve Plan of Management and Master Plan for public exhibition for a period of no less than 28 days and allow submissions to be received up until 42 days in accordance with section 38 of the Local Government Act 1993.
That Council endorse the proposed changes to the land categorisation and hold a public hearing under section 40A of the Local Government Act 1993.
In accordance with Council's resolution, the draft Merriman Reserve Plan of Management was forwarded to the NSW Department of Planning, Housing and Infrastructure on 26 March 2024 seeking consent to exhibit.
May 2023 - Preferred Master Plan Option
On 8 May 2023, Council's Environment and Planning Committee considered a report on the results of the public exhibition of the Merriman Reserve Master Plan options. The report was subsequently considered by Council at its meeting on 22 May 2023.
Council resolved:
That Council note the submissions received during the consultation for the draft Merriman Reserve Master Plan options.
That Council endorse the preparation of a preferred Merriman Reserve Master Plan option based on the exhibited Option 1.
That all persons who made a submission during the consultation for the draft Merriman Reserve Master Plan options be advised of Council's decision.
That a further report be considered by Council seeking endorsement to place a preferred draft Merriman Reserve Master Plan and Plan of Management on public exhibition for 28 days.
The preferred draft Merriman Reserve Master Plan will be refined and a further report will be presented to Council in the last quarter of 2023 seeking endorsement to place the preferred draft Master Plan and accompanying draft Plan of Management on public exhibition.
August 2022 - Public Exhibition of Master Plans
We've reviewed your feedback and worked with our partnering consultant, Group GSA, to develop two draft Master Plan options for Merriman Reserve. These Master Plan options were considered by Council at its meeting on 22 August 2022. Council resolved to place the two draft Merriman Reserve Master Plan options on public exhibition from 9 November to 9 December 2022.
November 2021 - Initial Community Consultation
Back in November 2021, we reached out to our community to gain feedback on Merriman Reserve. We wanted to know what you enjoy doing at the Reserve, what you wanted to see more of, what you think could be improved, and your vision for the future of the Reserve.
Do you need assistance reading and accessing this page?
For a free interpreter call us via the Translating and Interpreting Service (TIS) on 131 450
If you have a hearing or speech impairment, please contact the National Relay Service:
Voice Relay number: 1300 555 727
TTY number: 133 677
February 2025: Exhibition of the Master Plan and Plan of Management
A big thank you to our community, partners and stakeholders who have been with us throughout the planning process of Merriman Reserve. We are finalising our Master Plan and Plan of Management, which will help inform Council upgrades over the next 10 years. Since commencing the consultation in November 2021, we have received over 220 submissions and identified the following key themes:
Enhanced community access and amenities
Improved foreshore and beach access
Increased green spaces and recreational opportunities
Greater connectivity through pedestrian walkways and shared paths
If you would like to provide feedback or comments on the Plans, we encourage you to complete our online feedback form or return a hard copy submission. Consultation will be open from 5 February to 21 March 2025.
If you are returning a hard copy submission, please quote SF24/8017 - Public submission Merriman Reserve at the beginning of your submission and return in person to Georges River Council Civic Centre or Libraries, via email: mail@georgesriver.nsw.gov.au or post to PO Box 205, Hurstville BC NSW 1481
Pop-in to our Pop-up at Merriman Reserve Between 10.00am to 12.00pm, Saturday 22 February, our team will be on site at Merriman Reserve. Come along to chat with our staff and consultants about the Plans and ask us questions. No registrations required.
Attend our Pubic Hearing Under section 40A(1) of the Local Government Act 1993, Council is organising a public hearing into the proposed changes to the land categorisation of Merriman Reserve. The public hearing will be held on 4 March 2025 from 6:00 pm to 7:00 pm at Georges River Civic Centre, corner of MacMahon and Dora Streets, Hurstville. Register for the hearing
History and previous steps
March 2024 - Consent to Exhibit
On 11 March 2024, Council's Environment and Planning Committee considered a report presenting a draft Merriman Reserve Master Plan and Plan of Management for exhibition.
The recommendation of the Environment and Planning Committee was considered by Council on 25 March 2024 who resolved:
That Council notify the draft Merriman Reserve Plan of Management and Master Plan to the NSW Department of Planning, Housing and Industry, as the representative landowner of part of the land under section 39 of the Local Government Act 1993, to obtain owner's consent prior to public exhibition.
That Council seek written consent from the NSW Department of Planning, Housing and Infrastructure to adopt the draft Plan of Management, in accordance with section 3.23(6) of the Crown Land Management Act 2016.
That Council delegates authority to the General Manager to make any further amendments to the draft Merriman Reserve Plan of Management and Master Plan to address any points raised by the NSW Department of Planning, Housing and Infrastructure and make minor modifications to any numerical, typographical, interpretation and formatting errors if required.
That Council endorse the draft Merriman Reserve Plan of Management and Master Plan for public exhibition for a period of no less than 28 days and allow submissions to be received up until 42 days in accordance with section 38 of the Local Government Act 1993.
That Council endorse the proposed changes to the land categorisation and hold a public hearing under section 40A of the Local Government Act 1993.
In accordance with Council's resolution, the draft Merriman Reserve Plan of Management was forwarded to the NSW Department of Planning, Housing and Infrastructure on 26 March 2024 seeking consent to exhibit.
May 2023 - Preferred Master Plan Option
On 8 May 2023, Council's Environment and Planning Committee considered a report on the results of the public exhibition of the Merriman Reserve Master Plan options. The report was subsequently considered by Council at its meeting on 22 May 2023.
Council resolved:
That Council note the submissions received during the consultation for the draft Merriman Reserve Master Plan options.
That Council endorse the preparation of a preferred Merriman Reserve Master Plan option based on the exhibited Option 1.
That all persons who made a submission during the consultation for the draft Merriman Reserve Master Plan options be advised of Council's decision.
That a further report be considered by Council seeking endorsement to place a preferred draft Merriman Reserve Master Plan and Plan of Management on public exhibition for 28 days.
The preferred draft Merriman Reserve Master Plan will be refined and a further report will be presented to Council in the last quarter of 2023 seeking endorsement to place the preferred draft Master Plan and accompanying draft Plan of Management on public exhibition.
August 2022 - Public Exhibition of Master Plans
We've reviewed your feedback and worked with our partnering consultant, Group GSA, to develop two draft Master Plan options for Merriman Reserve. These Master Plan options were considered by Council at its meeting on 22 August 2022. Council resolved to place the two draft Merriman Reserve Master Plan options on public exhibition from 9 November to 9 December 2022.
November 2021 - Initial Community Consultation
Back in November 2021, we reached out to our community to gain feedback on Merriman Reserve. We wanted to know what you enjoy doing at the Reserve, what you wanted to see more of, what you think could be improved, and your vision for the future of the Reserve.
Do you need assistance reading and accessing this page?
For a free interpreter call us via the Translating and Interpreting Service (TIS) on 131 450
If you have a hearing or speech impairment, please contact the National Relay Service:
Under section 40A(1) of the Local Government Act 1993, Council is organising a public hearing into the proposed changes to the land categorisation of Merriman Reserve.
The public hearing will be held on 4 March 2025 from 6:00 pm to 7:00 pm at Georges River Civic Centre, corner of MacMahon and Dora Streets, Hurstville.
Please complete the following fields to register for the hearing.
Share Register for the Public Hearing on FacebookShare Register for the Public Hearing on TwitterShare Register for the Public Hearing on LinkedinEmail Register for the Public Hearing link
Share Feedback on the Master Plan and Plan of Management on FacebookShare Feedback on the Master Plan and Plan of Management on TwitterShare Feedback on the Master Plan and Plan of Management on LinkedinEmail Feedback on the Master Plan and Plan of Management link
Help plan the future of Merriman Reserve has finished this stage
Council is seeking feedback from the community on the future planning of Merriman Reserve. You can submit your feedback online or by returning a hard copy of the survey.
January - August 2022: Review of feedback and development of draft Plans.
Help plan the future of Merriman Reserve has finished this stage
Council will use feedback gathered from the community consultation period to inform and help shape the decisions proposed in the draft Plan of Management and Master Plan.
November - December 2022: Community Consultation of the Master Plan Options
Help plan the future of Merriman Reserve has finished this stage
With our community's feedback, we've worked with our consultant to develop two Master Plan options for Merriman Reserve. We're seeking further feedback before finalising the draft Plan of Management and Master Plan.
December 2022 - April 2023
Help plan the future of Merriman Reserve has finished this stage
Council will review the feedback gathered from the community consultation period to refine the Master Plan.
May 2023
Help plan the future of Merriman Reserve has finished this stage
Council will consider a report on the submissions received during the consultation for the draft Merriman Reserve Master Plan options and endorse a preferred option.
Public Exhibition
Help plan the future of Merriman Reserve is currently at this stage
Following Council endorsement of a preferred draft Master Plan and draft Plan of Management, the Plans will be on exhibition for a four week period. The community will have an opportunity to provide further feedback on the future of the Reserve. Council will consider this feedback before adopting these plans.